MOBILIZATION PLAN
TABLE OF CONTENT
1. INTRODUCTION
2. MOBILIZATION PLAN SCOPE
3. MOBILIZATION TEAM
3.1. Project Management
3.2. Planning and Permitting
3.3. Technical Team
4. ACTIVITIES WITHIN THE MOBILIZATION PLAN
4.1. Staff Recruitment
4.2. Procurement of Equipment
4.3. Securing Consents
4.4. Transfer of Records and Documents
4.5. Timescales and Key Tasks
4.6. Minimizing Disruption to the Public
1. INTRODUCTION
Download link given in the bottom
2. MOBILIZATION PLAN SCOPE
The Contractor will appoint and maintain a Mobilization Team for the duration of the Project until the Service Commencement Date. It will be made up as a minimum of:
- Project Management and Construction department to provide resource by means of technical support on engineering and construction considerations in relation to the Contract; and
- A Maintenance Manager to assist with resolution of any technical issues.
- Specifically, the Mobilization Team will work closely with the Project Manager to effect mobilization of the Contract to:
- Provide a smooth hand-over from all existing arrangements and activities leading up to the Commencement Date.
- Agree a set of activities with the client for all significant events during the mobilization period.
- Identify and work with activity specialists within the Contractors’ organization to ensure all appropriate policies and procedures are put in place in a timely and complete manner to ensure compliance with all aspects of the Contract obligations. The Contractor will provide the client with an adequate notice to existing sub-contractors where appropriate.
3. MOBILIZATION TEAM
The Mobilization Team will be organized by work stream.
3.1. Project Management
ABC will be Project Manager of the Mobilization Team, leading the construction of civil infrastructural facilities project through Close of Contract, the Planning Application and Permit Application for Service Commencement Date. He is familiar with all work streams in the project. Mohammad Murtadha Project Engineer will undertake the day to day project management of construction.3.2. Planning and Permitting
Plan has been prepared in coordination with the HSE plan, transportation/ consolidation plan and Dust control plan.
Upon authorization to proceed, mobilization activities will commence. The construction and set-up of the primary support/staging area of the project will take place. The west end of the site will be utilized as the primary support/staging area.
The primary support/staging area will be utilized to stage (2) excavators, (2) Bulldozers, (4) dumpers, (1) Diesel truck and (1) Low bed. South end will be utilized as a temporary employee/visitor parking area, while the east end and the centre as an excavated impacted fill stockpile area, a material staging area, a clean backfill stockpile area, and a stabilized construction entrance will be constructed.
3.3. Technical Team
The Technical Team will continue to be led by the Project Manager in the Project Management and Construction Group. The Project Engineer assists the leader by working closely with the Project Consultant and client’s representative. Maintenance Manager-Operators Maintenance ensures that all equipments and machines are in order and is responsible to the project Engineer.
4. ACTIVITIES WITHIN THE MOBILIZATION PLAN
4.1. Staff Recruitment
Recruitment of staff shall meet Iraq Local content requirement with Iraq Employment Bureau.
4.2. Procurement of Equipment
All procurement will be carried out in compliance with the Contractors procurement policies and methods.
4.3. Securing Consents
Alsoqoof Building Contracting LLC shall apply for and obtain Consents in its own name to carry out the Services in accordance with the Detailed Project Programme. As part of the preliminary arrangements the Contractor will liaise with the Client and the regulatory bodies accordingly to ensure that it is provided with all necessary data and information to enable application to be made to the relevant authorities for required Consents.
4.4. Transfer of Records and Documents
Prior to the Contract Commencement Date, Alsoqoof Building Contracting LLC shall establish a local project office, from where it will administer “a transfer of records” programme; subject is always to relevant data protection principles, where applicable. The Contractor will, as part as the overall mobilization plan, make arrangements for all relevant records, drawings, licenses and relevant certificates applicable and dedicated solely to the Project to be made available in order to arrange a smooth handover. The Contractor will ensure that from the early stages of the Contract, the flow of information and data is effective, accurate and auditable, so that informed management decisions can be made and Contract Key Performance Indicators, correctly reported in a timely manner.
4.5. Timescales and Key Tasks
Key Project Dates will be as indicated in Work Schedule to the project Agreement and which makes reference to the activities mentioned in this Mobilization Plan. A clearly defined programme for the startup of the will be developed in consultation with the Authority
4.6. Minimizing Disruption to the Public
The Contractor will provide an effective and efficient mobilization/transition plan, formulated in such a way as to cause minimal disruption to the general public, who are the end users of the services in question. During the mobilization/transition period and in accordance with its communications strategy developed for this project, the Contractor will